Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

Banner Left
Banner Right

Hauwanga delivers only 3 out of 506 houses

Ben Hauwanga

BH Properties, owned by businessman Ben Hauwanga, has only delivered three houses out of 506, two years after acquiring the land to build houses at the Ompumbu location in Oshakati.

The construction of the three houses and a few that are still at the ground levels, started in May last year.

Hauwanga told The Namibian yesterday that the construction of additional houses would start tomorrow.

He said construction of the houses stopped because there was a disagreement between the town council and the owners of the traditional homesteads in the vicinity.

He said the traditional homestead owners initially agreed with the town council to be compensated and leave the area for the construction to continue but they appear to have had a change of mind.

“As I am talking now, the town council went back on site and redesigned the second phase of the new plans because those people will stay there,” Hauwanga said.

He added that they had to stop because the main sewerage pipe was planned to pass through some of the traditional homesteads.

He added that if The Namibian calls him tomorrow, he will tell the journalist to go to the site and observe the progress.

Hauwanga said that the new plan was given to his company by the Oshakati Town Council last week.

Leonard Hango

DISAPPOINTED

Oshakati mayor Leonard Hango yesterday said the town council is disappointed with the pace at which BH Properties is working on the housing development.

He said the company could have started with water, electricity and roads first.

According to Hango, had this been done, it would have enticed people to buy houses at Ompumbu.

Hango said that the traditional homestead owners have already been compensated.

Oshakati Town Council chief executive Timoteus Namwandi yesterday said BH Properties were told to develop the site first, because banks would not finance houses not connected to bulk water suppliers.

He confirmed that the refusal by the traditional homestead owners contributed to the delay of the project.

A letter from BH Properties to the Oshakati Town Council dated 27 April last year showed that there was an unavailability of funds to start with the construction of the project in 2022.

“We have experienced unforeseen delays in our joint project due to the current downturn in the economy,” the letter reads.

“We have, however, recently made significant progress with the necessary funds to proceed with the construction by the end of May,” BH Properties wrote to the council.

In the letter, BH also promised to do “everything possible to minimise the inconvenience caused by the delay” and undertook “to alter our project scope in order to make up lost ground on the targets that have been set”.

PROMISES

Towards the end of May 2022, the Oshakati Town Council held a groundbreaking ceremony to hand over the site to BH Properties.

Hauwanga at the time said the three-year housing development was valued at N$305 million.

He said the project would provide employment to about 400 to 600 Namibians and that he would subcontract 20 contractors, who would be required to each complete a house every month.

“It means in 15 days, we will have 20 houses already from the floor level,” Hauwanga said in 2022.